A schedule is said to be "resource constrained" if what consequences become evident to the project manager during execution?

 A schedule is said to be "resource constrained" if what consequences become evident to the project manager during execution?

The precedence network duration cannot be met due to lack of resources.


The assignment of resources to one or more activities is overcommitted.