A study quoted by the text states that project network durations increase by approximately 40% when resources are applied. Why is this true?

 A study quoted by the text states that project network durations increase by approximately 40% when resources are applied. Why is this true?

Assigning resources may cause tasks to be delayed waiting on resource availability.

Reason:

The independent nature of work packages assumes all activities are independent and enough resources will always be available. Once real life (resources) is applied, things will happen slower or be intentionally delayed.