Put the steps used in the "parallel method" of resource constrained smoothing into their correct order.
Instructions
Choice 1 of 3. Assign resources to the activity with the smallest activity identification number. toggle button
Assign resources to the activity with the smallest activity identification number.
Choice 2 of 3. Assign resources to the activity with the smallest duration, unless there is a tie. toggle button
Assign resources to the activity with the smallest duration, unless there is a tie.
Choice 3 of 3. Assign resources to the activity with the minimum amount of slack, unless there is a tie. toggle button
Assign resources to the activity with the minimum amount of slack, unless there is a tie.
1. assign resources to the activity with the minimum amount of slack, unless there is a tie
2. assign resources to the activity with the smallest duration, unless there is a tie
3. assign resources to the activity with the smallest activity identification number