Put the steps used in the "parallel method" of resource constrained smoothing into their correct order.

 Put the steps used in the "parallel method" of resource constrained smoothing into their correct order.

Instructions

Choice 1 of 3. Assign resources to the activity with the smallest activity identification number. toggle button

Assign resources to the activity with the smallest activity identification number.

Choice 2 of 3. Assign resources to the activity with the smallest duration, unless there is a tie. toggle button

Assign resources to the activity with the smallest duration, unless there is a tie.

Choice 3 of 3. Assign resources to the activity with the minimum amount of slack, unless there is a tie. toggle button

Assign resources to the activity with the minimum amount of slack, unless there is a tie.

1. assign resources to the activity with the minimum amount of slack, unless there is a tie

2. assign resources to the activity with the smallest duration, unless there is a tie

3. assign resources to the activity with the smallest activity identification number