What happens to a time constrained schedule if executed with insufficient resources?

 What happens to a time constrained schedule if executed with insufficient resources?

The resource constrained schedule will be forced onto the plan.

Reason:

Optimistic views of resource availability will only delay the inevitable. You can make a project time constrained, but it can only get done as fast as the resources work.